Testing, Inspection & Commissioning

A fire protection system is not finished when the last pipe is fitted. It is finished when it has been proved to work — under pressure, at full flow, with every interface behaving as designed. That proof is what commissioning produces, and it is what an auditor or insurer will ask to see.

Water-based systems

  • Hydrostatic testing of above-ground and underground pipework, held and witnessed
  • Flushing of underground mains before connection
  • Fire pump acceptance testing — churn, rated and peak flow, with supply-versus-demand curves plotted against the design calculation
  • Valve and flow-switch verification, including tamper and supervisory signalling back to the panel
  • System balancing

Detection and alarm

  • Device-by-device verification across every loop
  • Cause-and-effect testing — confirming each alarm produces the right outputs: HVAC shutdown, damper closure, lift recall, shunt trip, suppression release
  • Notification coverage checks for sounders and strobes
  • Battery and standby capacity verification

Records that survive an audit

Commissioning to NFPA 3 produces a documented trail, not a verbal assurance. On completion you receive a System Record of Completion listing every certified device by type and count, test results with the values recorded, and signed work-completion certificates.

At TED Bernhardtz that record certified 127 detectors, 68 manual call points, 157 notification devices, 43 monitoring switches and every HVAC, damper and lift interface — each verified individually before handover.

Inspection of existing systems

We inspect systems we did not install — before a purchase, ahead of an audit, or when nobody can say when the pumps were last run. You get a written condition report and a prioritised list of what must be corrected to reach compliance.